Orange Avenue Update February 2024Orange Avenue Update December 2023Orange Avenue Update November 2023Orange Avenue Update October 2023Orange Avenue Update August 2023Orange Avenue Update February 2023Orange Avenue Update January 2023Orange Avenue Update October 2022Orange Avenue Groundbreaking Ceremony October 2022
Orange Avenue Update January 2023
Construction Status Report
Orange Ave I
January 3, 2023
Report/Pictures documenting the progress on Orange Ave I
- Demolition contract complete.
- Temporary Power is "ON" at the site.
- All underground site work has been completed.
- Water taps completed. Service main installed. Lateral building branches being installed.
- Building 1 foundation ready for Concrete Pour. We are delayed on this due to a revision needing to be approved by CoT. We have completed the resubmission. Waiting on clearance to proceed. Pour set for 1/10/23 Tentatively.
- Foundation crews working on Building 2. Concrete pour set for 1/10/23.
- Building 3 Underground plumbing complete. Concrete pour set for 1/17/23.
- Building 4 Underground plumbing complete. Concrete pour set 1/24/23.
- Building 5 Pad did not pass material testing. Crews are working on recompacting and completing final lifts. Concrete pour set for 1/31/23.
- Electrician has started placing underground conduit at Bldg. 3/4.
- Mad Dog team plans to distribute all job applications received to subs in January.
- THA Team has narrowed naming down to 2 options. (The Gardens @ South City, The Gardens @ Orange Ave)
- Lumber is still being delivered and stored onsite