Orange Avenue Update February 2024Orange Avenue Update December 2023Orange Avenue Update November 2023Orange Avenue Update October 2023Orange Avenue Update August 2023Orange Avenue Update February 2023Orange Avenue Update January 2023Orange Avenue Update October 2022Orange Avenue Groundbreaking Ceremony October 2022
Orange Avenue Update February 2023
Construction Status Report
Orange Ave I
February 3, 2023
Report/Pictures documenting the progress on Orange Ave I
- All underground site work has been completed. Corrections being made.
- Building 1 framing to start within the next two weeks. Trusses to be delivered to the site this week.
- Building 2 framing underway. Working on 2nd level.
- Building 3 Concrete pour set for 2/7/23. Weather permitting.
- Building 4 foundation work ongoing. Concrete pour set 2/10/23. Weather permitting.
- Building 5 Pad has passed testing. Plumber mobilizing to start underground installation.
- Mad Dog team plans to distribute all job applications received to subs in January.
- Final signage package pending from A1 Team. (The Gardens @ South City. A Columbia Residential Community)
- Lumber is still being delivered and stored onsite
- CoT Power has delivered conduit and transformer pads to the site for primary power. Installation ongoing.
- CoT Power delivery of site lighting conduit and pedestal bases pending.