Orange Avenue Update February 2024Orange Avenue Update December 2023Orange Avenue Update November 2023Orange Avenue Update October 2023Orange Avenue Update August 2023Orange Avenue Update February 2023Orange Avenue Update January 2023Orange Avenue Update October 2022Orange Avenue Groundbreaking Ceremony October 2022
Orange Avenue Update December 2023
Construction Status Report
Orange Ave I/II
December 8, 2023
Report/Pictures documenting the progress on Orange Ave I
- Site Work
- Landscape installation at bldg. 1-3
- Pool wrapping up. Tentative completion 12/15/23
- Comcast is onsite. Tentative completion 12/21/23
- Building 1
- Permanent power is "ON".
- Unit Acceptance walks scheduled for 12/18/23
- Building 2
- Permanent power is "ON"
- Unit Acceptance walks scheduled for 12/18/23
- Building 3
- Permanent power is "ON"
- Unit Acceptance walks scheduled for 12/18/23
- Building 4
- Permanent power pending.
- Paint ongoing
- Flooring ongoing
- Countertops ongoing
- Punch walks scheduled for 12/18/23
- Building 5
- Siding Installation ongoing
- Cabinets ongoing
- Flooring ongoing
- Paint ongoing.
- Punch walks scheduled for 12/22/23
- Phase II Site Work
- COT Conduit complete
- Phase II Building 1
- Exterior siding has started
- Tyvek ongoing
- Windows installation ongoing
- MEPF ongoing
- Insulation ongoing
- Brick work has started
- Phase II Building 2
- Exterior siding ongoing
- Tyvek ongoing
- Windows installation ongoing
- MEPF ongoing
- Insulation ongoing
- Brick work has started
- Phase II Building 4
- Hardware in progress.
- Tyvek has started
- Roof TPO/Shingle ongoing
- Window installation ongoing
- Brick work pending
- Phase II Building 5
- Hardware in progress
- Tyvek ongoing
- Roof TPO/Shingle ongoing
- Window Installation has started
- Brick work pending
- Phase II Building 3
- Framing Topped Out.
- TPO/Shingles pending
- Tyvek pending
- Phase II Building 6
- Framing Topped Out.
- TPO/Shingles pending
- Tyvek pending
- Phase III (Sebring & Bates)
- Letter of Recommendation given to THA.
- Contract pending HUD Approval